2018-04-19
迎著(zhù)烈日奮斗,頂著(zhù)困難前行
經(jīng)過(guò)一個(gè)月的前期周密準備,克服了多類(lèi)困難,蘇丹全國油庫系統安裝工作在45攝氏度以上的高溫下正式進(jìn)入實(shí)施階段!
After one month’s thorough preparation and overcoming various difficulties, Sudan Depot Management System enter into implementation stage officially with bearing the 45 degree’s high temperature.
根據預定實(shí)施計劃,油庫實(shí)施的各類(lèi)設備、實(shí)施人員已全部進(jìn)場(chǎng)并啟動(dòng)第一階段的實(shí)施工作。油庫系統節點(diǎn)為本次實(shí)施的最后一個(gè)節點(diǎn),在油庫實(shí)施完成后將全面形成油庫庫存管理→油庫發(fā)油管理→油站地罐交接管理→油站銷(xiāo)售管理的閉環(huán)模式,屆時(shí)蘇丹國家石油公司的成品油儲存零售運輸整體方案將更加完善。
According to the implementation plan, the implementation start with all the relative implementation devices and stuffs’ deployment in the depot have been accomplished. Depot implementation node is the last milestone of this project. The full aspect linked and closed cycle management of the refined oil retail management system will be realized when the depot implementation is accomplished: Depot storage management→Depot Oil distribution manage ment→Station tank storage handover management→Station sales management. Then the overall solution of refined oil storage, retail and delivery management system of Sudan National Petroleum Company will be promoted to a more perfect level.
為保證油庫實(shí)施的順利進(jìn)行,由蘇丹國家石油公司組織的油庫項目實(shí)施前協(xié)調及啟動(dòng)會(huì )4月2日在蘇丹石油部召開(kāi)▼
In order to ensure the smooth implementation of the oil depot, the pre coordination and start-up of the oil depot project organized by Sudan National Oil Company was held in Sudan Petroleum Ministry in April 2nd.
針對《油庫現場(chǎng)實(shí)施安全手冊》及《油庫實(shí)施作業(yè)標準》,4月7日開(kāi)工前在GADRA油庫現場(chǎng)協(xié)同油庫消防安全部門(mén)進(jìn)行安全培訓,并啟動(dòng)第一批油庫的實(shí)施工作▼
Base on the Depot safety implementation manual and Depot implementation standard, We carried out a safety training to all the implementation related staffs together with depot fire department on 7th April in Gardra depot. At the same time, we declared the starting of the depot implementation.
為保證實(shí)施進(jìn)度及實(shí)施質(zhì)量,三盈產(chǎn)業(yè)集團蘇丹項目部在每個(gè)實(shí)施現場(chǎng)指派質(zhì)量監督人員,負責全程質(zhì)量監督及實(shí)施計劃的推進(jìn)。
For guarantee the implementation quality and schedule, SANKI Sudan project appoint quality supervisors in each implementation field. The supervisors are responsible for quality supervision and promoting the implementation process.
▲現場(chǎng)消防系統測試
Fire extinguish device testing in real field
▲管路鋪設現場(chǎng)監督
Cable pipe layout supervision
▲清罐前與實(shí)施人員進(jìn)行安全再溝通
Communicate with tank clearance team before begin work
▲發(fā)油臺改造現場(chǎng)安全及質(zhì)量監督
Flow meter section pipe modification field and the corresponding supervision
▲中方人員與油庫負責人安全問(wèn)題溝通
Communication between SANKI engineer and depot safety chief on safety issues
三盈產(chǎn)業(yè)集團蘇丹項目部再次攻克重要節點(diǎn),在工作過(guò)程中彰顯了三盈人不怕困難、奮勇向前的可貴精神,我們將繼續在非洲大地上為“中國制造”爭光添彩!
SANKI group Sudan conquer another key node, this overcoming manifest our SANKI staffs’ courage in facing difficulties, persistence and determined exploiting spirit. We are going to earn more praise in the name of SANKI for “Made in China” on this vast ancient African earth.